SDE Electrical worked closely with Gridserve to carry out a feasibility study into installing a new bay of 8 high powered ABB car chargers with Dobbies Speke. This was all powered from a new Sub Station installed by ourselves and the SDE Group.

Our electrical services included:
- Installation
- Servicing
- Test and inspection

This was all powered from a new  Sub Station installed by ourselves and the SDE Group:

4 x 4  ABB 184 High powered Car charger posts
4 x 4 ABB 175 High Powered Car Charger posts

-Install 185mm HO7 cables to each of the 8  Charger 175kw Power Cabinets
- Install 185mm HO7 Cables from Cabinets to Charger posts
- Install Data Cat 6 and Fibre Optic cables to each Charger post
- Fit install and Connect  LV , Comms and Scarda Panel
- Fit, Install, Connect and Carry out Electrical Tests on all Cables and Car Chargers.
- Commission of All the Car Chargers